Skybox and ct location

True Hybrid Energy System
Post Reply
goldserve
Forum Expert
Posts: 68
Joined: Mon Jun 27, 2022 3:06 pm
My RE system: Skybox inverter
Battery: 2 x EG4 100A lifepo4 batteries & 1 x SOK 100A battery, total 15kWh
16 x REC260 panels, 2 strings of 8
Grid-tied, net metering with TOU
Location: NorCal, PGE

Skybox and ct location

Post by goldserve » Fri Sep 01, 2023 7:11 am

I’m reorganizing my panels and wiring a little. I was planning on moving the grid connection upstream but the external ct would not capture the current usage of the inverter. Is this okay?

I put a main panel before my current main panel so hence the possible upstream relocation but the cts are still on the feeder of my current main panel.

Post Reply